What is an inspection and test plan (ITP)?
Pro Site Docs · Guide
An inspection and test plan sets out what will be checked as the work is built, who checks it, against what standard, and what evidence gets kept. It is a quality document rather than a safety one — and that distinction is where most of the confusion starts.
It is contractual, not statutory
No UK regulation requires an ITP by name. It is normally required by the contract or the client specification, and on anything with a quality plan behind it you will be asked for one before you start. That does not make it optional in practice: on utilities, highways, rail and most public sector work, no approved ITP means no permission to proceed.
What goes in one
An ITP is usually a table, worked through in construction sequence. Each row covers an activity, the specification or standard it is being checked against, the type of check, who does it, and what record results. The part that gives an ITP its teeth is the hold and witness points.
- Hold point — work must not continue past this until it has been signed off. Concrete does not get poured until the reinforcement has been inspected.
- Witness point — the client or their representative is invited to attend, but work can proceed if they do not.
- Review point — records are submitted and reviewed after the event.
Who signs it off
Typically your own quality or site engineer for the internal checks, and the client’s representative or clerk of works at hold and witness points. Get the ITP agreed before work starts. An ITP approved halfway through a job leaves you arguing about what should have been inspected on the sections already covered up.
The common mistakes
Writing an ITP that lists every conceivable check, then failing most of them because nobody could realistically do them all. Setting hold points at moments where stopping is impractical. And leaving the evidence column vague — “records kept” is not a record. Name the form.
Get the documents ready-made
Our Audit & Inspection Pack gives you editable inspection and test records to adapt to your specification, or take single documents.
Editable inspection, test and audit templates for UK construction — structured records ready to adapt to your specification.
See the inspection packLee Hunt — SMSTS · NEBOSH NG1 & NG2 · NEBOSH Health & Safety Leadership Excellence · CSCS Black Card · Level 6 Diploma in Construction Site Management · IOSH · ISEP (environmental) · Temporary Works Supervisor & Coordinator · Lift Supervisor. Last reviewed: 29 August 2026.
Templates for this
Keep reading
General guidance only. This article explains how the rules generally work in UK construction. It is not advice for your specific site, task or project, and it is not legal advice. Your own risk assessment, method statement and arrangements must be prepared and checked by a competent person for the actual work being done.